APD are engineers with over a 100 years of collective experience in delivering control systems, automation and SCADA projects.

EAST ROCKINGHAM WASTE TO ENERGY GENERATOR GRID CONNECTION

The 28.6 MW Waste to Energy plant is situated in East Rockingham, WA and is designed to deliver a cost-effective waste treatment solution and source of dispatchable renewable energy, whilst achieving a 96% diversion of residual waste from landfill. It connects to the grid via Western Power’s Office Rd 132kV (OFE) substation, a greenfield substation…

STATE-OF-THE-ART ‘LAB’ NOW A 60 SQUARE METRE TESTING ENVIRONMENT

APD Engineering’s state-of-the-art ‘Lab’ at the Perth Head Office, has once again increased its footprint! The unprecedented demand on our testing environment means that the now 60 square metre secure area, serves to further cater for various new HV Substation Protection & Automation projects. This most reliable asset allows APD to simplify the problem elimination…

COLLIE & MUJA POWER STATIONS WEM REFORM SUBSTATION AUTOMATION UPGRADE

Synergy’s Collie & Muja Power Stations are situated in South West region of Western Australia and are subject to the Wholesale Electricity Market (WEM) Reform work program, which required the upgrade of the substation automation systems at these sites, to enable real-time market-driven controls from the Independent Systems Operator, AEMO, to be implemented. Western Power…

CHICHESTER SOLAR FARM OWNER’S ENGINEER

APD Engineering were engaged by Alinta Energy to provide Owner’s Engineering services for the Chichester Solar Farm. The Chichester Solar Project consisted of a 60MW solar PV power station located in the Pilbara region. The project also included 64km of 220kV transmission line, two new 220kV substations at Christmas Creek and Cloudbreak and an expansion…

Transgrid Berrybank Wind Farm Substation and Switching Station Automation

TRANSGRID BERRYBANK WIND FARM SUBSTATION AND SWITCHING STATION AUTOMATION

APD was engaged by TransGrid to provide the automation configuration, testing & commissioning support works for the greenfield Berrybank wind farm connection substation (BBW) and switching station (BBS). Berrybank 1 wind farm is located in south-western Victoria, approximately 130km west of Melbourne. It is based on 43 Vestas V136-4.2MW wind turbines, with a total installed…