FORSTER RD MT WAVERLEY HV LINE RELOCATION
APD has been engaged to provide full electrical engineering, project management and as built detailing for the Forster Rd, Mt Waverley HV line relocation between Ferntree Gully Rd. and Waverley Rd.
HV Transmission and LV Distribution Power line & cable design is one of APD Engineering’s core businesses offering clients in the utilities, mining, oil and gas and land development sectors low to high voltage networks (415v – 330kv), overhead and underground installations, lattice tower and monopole structures.
APD has been engaged to provide full electrical engineering, project management and as built detailing for the Forster Rd, Mt Waverley HV line relocation between Ferntree Gully Rd. and Waverley Rd.
APD were selected as the successful electrical consultant to deliver complete designs and project management of the electrical and communications infrastructure for The Dunes Estate land development.
Provision of electrical design as per AS/NZS 3000, AS/NZS 1158 lighting design and nbn third-party pit & pipe design for the Southlink Cockburn commercial development.
APD Engineering were engaged by ElectraNet to undertake Insulation Coordination and Reactor Switching Studies for a 275kV substation in South Australia. Advanced studies based on PSCAD/EMTDC modelling were carried out to ensure the safe operation of the substation through surge protective devices.
APD were engaged by Essential Energy to complete large packages of reinforcement works as part of their network maintenance. This included both overhead and underground design packages all over NSW.
Secondary scope to facilitate reconfiguration of 66kV transmission lines connecting to the Alinta Power Station on the BHP network.
APD has been engaged to provide full electrical engineering, project management and as built detailing for the Canterbury Rd Braeside industrial Estate.
Southern Cross Electrical Engineering (SCEE) engaged APD to do power line modelling and design for the 66kv reconfiguration outside of Yarnima Substation to the Newman township. We completed a field inspection determining the reconfiguration required additional poles and modification of loads to existing poles and towers be reassessed. APD then provided cost effective design solutions for the new power poles and modifications to the existing power poles and towers.
APD Engineering were contracted by PLP to engineer and design three new 1.5MVA and one 1MVA 11/0.433kV kiosk substations, powerline modifications and power and fibre optic cable reticulation for Rio Tinto Iron Ore’s Wickham Accommodation Expansion.
Tom Price Transmission Tower: APD were engaged by Rio Tinto & Powerlines Plus to conduct detailed designs for the replacement of a damaged tower in WA