TALLAWARRA B GRID CONNECTION

APD Engineering was engaged by Energy Australia (EA) to carry out a grid connection study & assess the local network & determine what upgrades were required to allow connection of a further 300-450MW extra generation to the Endeavour Energy’s (EE) 132kV Tallawarra Switching Station. It will be Australia’s first net-zero emissions plant, which will use…

CHICHESTER SOLAR FARM OWNER’S ENGINEER

APD Engineering were engaged by Alinta Energy to provide Owner’s Engineering services for the Chichester Solar Farm. The Chichester Solar Project consisted of a 60MW solar PV power station located in the Pilbara region. The project also included 64km of 220kV transmission line, two new 220kV substations at Christmas Creek and Cloudbreak and an expansion…