CLIENT: BGC CONSTRUCTION FOR HITACHI
LOCATION: Forrestdale, WA.
SCOPE:
 Engineering, Procurement and Construction (EPC).
TECHNICAL SITUATION
APD was required to extend Telstra’s communications pit and pipe over 1km:
- Engineering feasibility assessment for Hitachi high load vehicle route;
 - Facilitation of undergrounding works for existing Western Power assets impacting route;
 - Detailed 3rd Party Pit & Pipe Design to Telstra Specifications and Metropolitan
 - Redevelopment Authority (MRA) approval;
 - Location of other utility services in the vicinity of proposed works;
 - Supply, excavation and install of pit and pipe infrastructure including directional drilling under Tonkin Hwy and Mandrel testing;
 - Coordination with micro-tunnelling contractor responsible for installation of water and sewerage services under Tonkin Hwy;
 - Liaison with BGC Construction and other subcontractors to agree on suitable work schedule
 - Preparation of Traffic Management Plans for lane closures and permits with Main Roads WA;
 - Provision of all QA documents and testing results to Telstra to facilitate project handover.
 
SERVICES PROVIDED
- Detailed 3rd Party Pit & Pipe Design;
 - Procurement & Construction Management;
 - Project & Contract Management;
 - Site Specific Quality Management System Implementation;
 - Traffic Management Plans and Site Implementation;
 - Coordination of Underground Services and Authorities.
 